Texas Governor Greg Abbott has ordered a temporary halt on new data center grid connections, directing state regulators to audit facilities before they can connect to the power grid. The move comes as ERCOT faces 474 gigawatts of connection requests—90% from data centers—which is five times the state's peak demand. While the Data Center Coalition hopes the audit will highlight responsible actors, political rivals Gina Hinojosa and Sid Miller have dismissed the pause as empty rhetoric ahead of the 2026 election.
Aug 10, 2026 · 1 source