The Finnish Licensing and Supervision Agency (LVV) has ordered Google subsidiary Tuike Finland Oy to halt preparatory construction at planned data center sites in Muhos and Kajaani by October 23, 2026. The suspension follows revelations that Google cleared over 500 hectares of forest without completing mandatory environmental impact assessments. Google, which recently announced a landmark €13 billion digital infrastructure investment in Finland, acknowledged it fell short of its standards and pledged to comply with regulatory guidance while advancing a 130-hectare tree-planting remediation plan.
The regulatory suspension order
- ▪The Finnish Licensing and Supervision Agency ordered Tuike Finland Oy to explain its preparatory work at the Muhos and Kajaani sites and outline future plans by October 14, 2026, warning of potential enforcement proceedings and fines
- ▪The Finnish Licensing and Supervision Agency's suspension order for the Muhos and Kajaani data center sites applies to tree removal, topsoil stripping, excavation, quarrying, crushing, soil mass transfer, ditching, and road and storage area construction
- ▪The Finnish Licensing and Supervision Agency ordered Google subsidiary Tuike Finland Oy to suspend preparatory building work in Muhos and Kajaani by October 23, 2026, for clearing hundreds of hectares of forest without completing mandatory environmental impact assessments
Impact of the forest clearing
- ▪Finnish Association for Nature Conservation chair Hanna Halmeenpaa stated that nature sites that should have been preserved were logged, turning Google's data center site in Muhos into a sandy area
- ▪Tuike Finland Oy cleared approximately 330 hectares of forest in Muhos and just under 200 hectares of forest in Kajaani prior to completing the environmental impact assessments
Google's response and remediation
- ▪Google acknowledged it fell short of its own standards regarding its Finland data center construction and stated it acted in good faith under the Forestry Act by running nature surveys and protecting high-value areas
- ▪Google announced plans to advance landscaping and biodiversity efforts in Finland, which include planting trees across 130 hectares in Muhos
Finland's data center boom
- ▪Google announced a €13 billion investment in Finland's digital infrastructure, spanning Muhos, Vaala, Kajaani, and Hamina, marking its largest single investment in Europe
- ▪Finnish Association for Nature Conservation chief operating officer Tapani Väistölä stated that Finland's overheated data center market forces data center developers to accelerate processes, placing excessive pressure on small municipalities
- ▪Finland has become a key location for AI data centers, dubbed the 'Texas of Europe,' due to its cool climate, available land, and low-carbon electricity
Environment Minister's response
- ▪Finland's Minister of the Environment and Climate Sari Multala stated that it was a serious matter if Google and its subcontractors had acted as alleged in clearing forest without completing environmental assessments
- ▪Finland's Minister of the Environment and Climate Sari Multala stated that environmental assessment problems at the Muhos and Kajaani sites would likely delay Google's data center projects
Debatable claims
- ▪Google's unauthorized forest clearing in Finland represents a systemic failure of corporate accountability
- ▪Google's planned ecological restoration in Muhos is sufficient to offset its unauthorized forest clearing
- ▪Finland's halt on Google's data center construction is justified
- ▪Finland should prioritize environmental preservation over Google's thirteen-billion-euro digital investment