Oracle's stock fell over 4% on September 24, 2026, after reports revealed the company sent a force majeure notice to Blue Owl Capital regarding Project Jupiter, a massive $50 billion AI data center in New Mexico. The legal move aims to shield Oracle from cost increases and delay payments if the project misses its 2028 launch. While Oracle and Blue Owl insist they remain aligned and on schedule, the project faces severe infrastructure setbacks, including a delayed natural-gas pipeline and pending air permits, amid mounting local and environmental opposition.