NTT Data Group Corp. plans to invest at least $9 billion through 2033 to quadruple its Japanese data center capacity to 1 gigawatt, addressing soaring demand for artificial intelligence infrastructure. The expansion includes adding 750 megawatts of capacity, starting with a 100 megawatt facility in Tochigi Prefecture in 2027. However, the expansion faces severe bottlenecks due to Japan's power grid constraints, which can delay electricity connections by up to a decade in key regions.